Silver Line on Track

Originally published 12/6/17

According to Federal Transit Administration officials, all six Phase 2 Metro stations are in the building phase, and collectively at about 74% completion. Power has been turned on to some segments of the track near the Center for Innovative Technology.

 

Currently the Silver Line ends at Wiehle-Reston, but Phase 2 will add six more stations, including Dulles Airport. All stations will have the same standard design features we are accustomed to, except for Dulles, which will mimic the strong lines of this iconic landmark. There will be no new parking associated with this station.

 

The six stations beyond Wiehle-Reston are Reston Town Center, Herndon, Innovation Center, Dulles Airport, Loudon Gateway, and Ashburn. All six stations will open for passengers concurrently, and current projections places the opening date in early 2020.